NJ officials plan to avoid 'Super' power failure

by KIX 101.1/ 1230 KFJB Sports Department posted Nov 15 2013 11:09AM

EAST RUTHERFORD, N.J. (AP) - With the memory of last February's Super Bowl power outage front and center, officials have laid out plans for how they plan to avoid a similar problem at MetLife Stadium in February.

The head of Public Service Electric & Gas says the utility is running a third power line into the electrical substation at the Meadowlands sports complex. PSE&G president Ralph LaRossa said Thursday that even if two of the power lines fail, the third would be enough to power the complex.

LaRossa said the Super Bowl site will require abot 18 megawatts of electricity, or about what it takes to power 12,000 homes.

A partial power outage that caused a 34-minute delay at the Superdome was blamed on an electrical relay device installed specifically to prevent a power failure.

Filed Under :
People : Ralph LaRossa
11/15/2013 11:09AM
NJ officials plan to avoid 'Super' power failure
Please Enter Your Comments Below
Title :
Comment :
On Air Now
Kix Listener Club
Recent Posts
Iowa officer wounded in gun range accident
Chinese man released on bond in trade secrets case
Iowa woman arrested after child falls from window
Panel clears tax rebate for Knoxville Raceway
Iowa delays plan to move inmates out of old prison
Tag Cloud
Categories 
Archives